Production Plant Move
Own label producer TESCO, ASDA Sainbury’s, M&S etc.
October “Move this to Bradford as soon as you can. Keep Sainsbury’s and M&S business. Make it pass M&S audit. Tell us what it will cost. Do it on cost on time.”

Outcome
- Time
- Start planning September
- Produced 42 alternative solutions before the final layout.
- Asbestos removal starts December
- Stock of Sainbury’s product to end of August
- Production by July.
- Move costs (in addition to £6.4M for plant & product).
- Total budget £3.028M.
- Actual spend £3.032M.
- No reportable accidents or other unplanned events.
The destination in Bradford looked like this…

Blow moulding and bottle supply

9 months later up and running in July the following year…

Syrup mixing on the same soft drinks manufacturing project. 20,000lt made in 20 minutes!
Issues
- There was not space on the Bradford site. A new adjacent location was found and converted to M&S food manufacture standards.
- After the site became available for survey:
- The planned position for 4 x 60 tonne tanks was found to have 15 metres of land fill. Tanks relocated to a position where the bed rock was 1m below ground.
- The planned position for 5 x 20 tonne mixing tanks was found to have a duct (2.5m x 3.5m) under it. Tanks moved to solid base area.
- Voids found under floors which had to be filled with grout.
- Insufficient power supply. A new 2MVA supply was negotiated with the site landlord and Yorkshire electricity. Installation managed by the project team.
- Poor support from original equipment suppliers, who would rather have supplied new equipment so solutions had to be found in-house.