Princes

Princes International Food and Drink GroupProduction Plant Move

Own label producer TESCO, ASDA Sainbury’s, M&S etc.

October “Move this to Bradford as soon as you can. Keep Sainsbury’s and M&S business. Make it pass M&S audit. Tell us what it will cost. Do it on cost on time.”

Princes_0001

Outcome

  • Time
    • Start planning September
    • Produced 42 alternative solutions before the final layout.
    • Asbestos removal starts December
    • Stock of Sainbury’s product to end of August
    • Production by July.
  • Move costs (in addition to £6.4M for plant & product).
    • Total budget £3.028M.
    • Actual spend £3.032M.
  • No reportable accidents or other unplanned events.

The destination in Bradford looked like this…

Princes_BD1

Blow moulding and bottle supply

Princes_0005

9 months later up and running in July the following year…

 Princes_finished

Syrup mixing on the same soft drinks manufacturing project. 20,000lt made in 20 minutes!

Princes-composite 

Issues

  • There was not space on the Bradford site. A new adjacent location was found and converted to M&S food manufacture standards.
  • After the site became available for survey:
    • The planned position for 4 x 60 tonne tanks was found to have 15 metres of land fill. Tanks relocated to a position where the bed rock was 1m below ground.
    • The planned position for 5 x 20 tonne mixing tanks was found to have a duct (2.5m x 3.5m) under it. Tanks moved to solid base area.
    • Voids found under floors which had to be filled with grout.
  • Insufficient power supply. A new 2MVA supply was negotiated with the site landlord and Yorkshire electricity. Installation managed by the project team.
  • Poor support from original equipment suppliers, who would rather have supplied new equipment so solutions had to be found in-house.